| Month | Draw This Month ($) | Outstanding Principal ($) | Monthly Interest ($) | Cumulative Interest ($) |
|---|
Most construction loans accrue interest only on funds disbursed. Instead of paying interest out-of-pocket each month, borrowers often set aside a reserve account that automatically covers the charges. Lenders advance interest from that reserve as part of each draw, ensuring payments remain current even when the building has yet to generate income. The Construction Loan Interest-Reserve Planner helps you size that account, anticipate when it may run dry, and adjust the draw schedule to stay within underwriting limits.
Interest reserves are especially important for developers, custom home builders, and investors renovating multifamily properties. They allow you to keep liquidity focused on hard costs and contingency items. However, underestimating reserve needs can trigger emergency capital calls or trigger default clauses. This tool makes the invisible cash burn visible by simulating month-by-month draws and interest accruals.
The loan overview section captures the commitment amount, nominal interest rate, and expected construction duration. You can add optional buffers such as a contingency percentage applied to the final reserve recommendation and any interest-only months after completion (useful when projects require a lease-up period before converting to permanent financing).
The draw schedule accepts as many entries as needed. Each draw includes a month number (starting at one) and the amount funded in that month. The planner assumes funds are advanced at the start of the month, making the entire balance subject to that month’s interest accrual. If your lender accrues daily, this still offers a reasonable approximation—especially when you keep draw months aligned with payment cycles.
Interest-only construction loans calculate monthly interest as outstanding principal multiplied by the monthly rate. If Dm is the draw amount in month m, the principal after month m is the running sum of draws:
The monthly interest charge Im is then:
where r is the annual interest rate expressed as a decimal. The cumulative interest is the running sum of monthly charges. The tool aggregates these values, then adds your contingency percentage to produce a recommended reserve. Any post-completion interest-only months simply continue accruing interest on the final principal balance.
Imagine a $1,200,000 construction loan at 7.5% interest across a 12-month build. The project draws $200,000 in month one, $300,000 in month three, $400,000 in month six, and $300,000 in month nine. Interest accrues as each draw posts. By month nine, the outstanding principal reaches the full $1.2 million, and monthly interest climbs to $7,500. Summing all monthly charges yields $48,750 in interest during the build. Adding a 10% contingency lifts the recommended reserve to $53,625. If the lender also requires three months of interest-only payments after completion while the property leases up, the reserve needs to cover an additional $22,500, bringing the total to $76,125.
The planner reveals not only the final number but also the timing of cash burn. For example, the reserve balance dips quickly after month six when large draws compound interest. Armed with this insight, you can negotiate your draw schedule, adjust contingency buffers, or plan capital contributions in advance.
The results panel summarizes the base interest reserve requirement, the contingency amount, and the total recommended reserve. The table shows month-by-month accruals so you can spot spikes. If a month displays an exceptionally high interest charge, consider splitting large draws into smaller tranches or aligning them with sales milestones. Developers often coordinate draws with inspection checkpoints to smooth interest loads.
The downloadable CSV makes it easy to share schedules with lenders, co-investors, or project managers. Import the file into your pro forma to ensure carrying costs remain funded throughout the build. Because interest reserves are often capitalized into the loan, this planner also flags when you might exceed the original budget, prompting early discussions with your lender.
The table below compares reserve needs for different draw pacing strategies.
| Draw Strategy | Months to Fully Draw | Total Interest During Build | Reserve with 10% Contingency | Post-Completion Carry (3 months) |
|---|---|---|---|---|
| Front-Loaded (60% in first quarter) | 4 | $61,800 | $67,980 | $18,540 |
| Evenly Distributed | 12 | $48,750 | $53,625 | $22,500 |
| Back-Loaded (major draw at month 9) | 10 | $42,900 | $47,190 | $22,500 |
This planner assumes interest accrues monthly on the balance outstanding at the start of each period. Daily accrual, variable-rate indexes, rate caps, or rate floors are not modeled. It also assumes every draw clears on the first day of the stated month and that reserves are held in a non-interest-bearing account. In reality, lenders may release draws mid-month, escrow interest separately, or allow reserve balances to earn credit. Always confirm calculations with your lender’s closing statement and adapt inputs to match the draw schedule approved in your construction loan agreement.
Interest reserves are not just a spreadsheet exercise; they shape conversations with everyone on the project team. Share the monthly interest schedule with your lender so they can align inspection timing and draw approvals. If a draw pushes the loan-to-cost ratio beyond limits in a given month, you can renegotiate the distribution or sequence of work. Contractors also appreciate visibility. When they know which month a large draw is scheduled, they can sequence crews accordingly, reducing idle time and change orders. This collaboration can shave weeks off the build, which directly lowers interest costs.
The calculator’s CSV export is particularly handy during weekly project meetings. Print the schedule or upload it to your project management software. Annotate each month with milestone targets—foundation, framing, rough-ins, finishes—so that everyone understands the financial implications of delays. If a subcontractor requests accelerated payment, you can show how moving a draw impacts interest and whether contingency funds should be tapped to keep the reserve intact.
Finally, communicate with appraisers and inspectors early. Some lenders require third-party verification before releasing each draw. Knowing the reserve timeline helps you schedule inspections proactively. If a delay occurs, update the calculator and circulate the revised reserve requirement so investors are not surprised by additional carry costs.
Developers often maintain dynamic pro formas that track hard costs, soft costs, financing expenses, and expected returns. The interest reserve planner feeds directly into that model. By exporting the monthly data, you can align interest accrual with rent-up assumptions, absorption rates, or sales closings. If your exit strategy depends on hitting a particular yield-on-cost, plugging in accurate reserve numbers is essential.
Use the data to run sensitivity analyses. What happens if a key draw slips by two months? Duplicate the schedule, shift the draw month, and recompute the total interest. The delta becomes your contingency requirement for schedule risk. You can also test alternative capital stacks, such as mezzanine debt or preferred equity, by comparing how different funding sources alter the outstanding principal at each stage. This level of detail strengthens investor updates and demonstrates disciplined financial stewardship.
Remember to adjust for interest capitalization rules. Some accounting frameworks allow you to capitalize interest into the cost basis of the project, while others require expensing it as incurred. Tag each monthly interest entry accordingly so your accounting team can book transactions correctly. Maintaining this audit trail shortens year-end reviews and keeps lenders confident in your reporting accuracy.
No construction project goes exactly as planned. Material price spikes, weather delays, or permitting surprises can all increase the interest burden. Consider building layered contingencies: one for hard costs and another specifically for interest reserves. The calculator’s contingency field gives you a baseline, but you can run multiple scenarios with higher percentages to prepare for adverse events. Document which triggers—such as a two-week delay or a 5% material increase—would cause you to tap additional funds.
Insurance products like builder’s risk policies may cover certain delays. Cross-reference policy coverage with the interest schedule to determine whether claims could offset reserve depletion. Additionally, explore rate-lock options on your construction loan; some lenders allow you to cap the floating rate for a fee. Enter that fee as part of the contingency to see whether it provides value relative to potential rate hikes.
Lastly, plan for the transition to permanent financing. If the project will roll into a permanent loan or be sold upon completion, ensure the interest reserve lasts through stabilization. Add expected lease-up months to the interest-only field so your reserve includes the carry period. Investors appreciate seeing that you have budgeted beyond the certificate-of-occupancy date, acknowledging the real-world lag between completion and cash flow.