This electric school bus depot charging scheduler helps fleet managers, school districts, consultants, and utilities test whether a depot can reliably recharge buses between afternoon pull-in and morning rollout. By combining bus counts, battery sizes, charger power, time windows, and demand limits, it provides a quick feasibility check and an estimate of overnight energy costs.
The calculator uses a simplified energy and power model to approximate whether your current or planned depot design can fully recharge the fleet in the available overnight window. It focuses on four core ideas:
At a high level, the tool compares total energy needed with the maximum energy that can be delivered without exceeding your charger capacity or demand limit. It then estimates cost using off-peak and on-peak energy prices, plus an optional demand charge for power drawn above your chosen limit.
The underlying calculations are intentionally simplified for planning purposes. Conceptually, the core quantities are:
This depends on the difference between the state of charge (SoC) when buses return and the target SoC at departure, multiplied by battery capacity:
Where:
The calculator may also cross-check this against the daily route energy per bus input as a reasonableness check.
If all buses are similar, the total energy is approximately:
Total fleet energy ≈ Number of buses × Energy needed per bus
The maximum energy your depot can deliver within the charging window is limited by both the chargers and the site demand limit:
Charger-limited power (kW) = Number of active charger ports × Power per charger
Allowed site power (kW) = min(Charger-limited power, Site demand limit)
Maximum deliverable energy (kWh) = Allowed site power × Available charging window (hours)
Energy cost is broken into off-peak and on-peak based on how the schedule fits into your window. The tool multiplies kWh in each period by the respective rate and, if your simulated load exceeds the demand limit, adds a marginal demand charge above limit per kW above that cap.
Use these inputs to describe your depot and routes:
After you enter values, run the calculation to see whether the fleet can be fully charged in time, what the approximate overnight energy use is, and how demand and energy rates affect cost.
The tool is designed to highlight whether your configuration is feasible and where bottlenecks appear. Typical outputs and how to interpret them include:
Operations and facilities teams can use these outputs to decide whether to adjust route blocks, add chargers, upgrade service, or negotiate different tariffs with the utility.
Consider a mid-size suburban depot similar to the default values:
For each bus, the SoC increase from 35% to 90% is 55 percentage points. Applied to a 210 kWh battery, that is about 115.5 kWh per bus. For 48 buses, the total required energy is roughly 5,544 kWh, plus some margin from the operational buffer.
The charger-limited power is 18 × 60 kW = 1,080 kW. With a 900 kW demand limit, the tool will cap instantaneous power at 900 kW. Over a 12-hour window, the theoretical maximum deliverable energy at that cap is 10,800 kWh, which is well above the 5,544 kWh requirement. The scheduler therefore focuses on whether all buses can rotate through the available ports within 12 hours while respecting that 900 kW cap.
If the results show the plan is feasible, you can explore variations:
Using the same structure, you can compare multiple investment options without building a full simulation model.
The table below illustrates how different depot configurations might behave in the scheduler. These are conceptual examples; use your own data for decisions.
| Scenario | Typical Fleet Size | Charger Type & Count | Charging Window | Demand Limit | Likely Outcome in Tool |
|---|---|---|---|---|---|
| Small rural depot | 10–15 buses | 10 × 25 kW (Level 2 / low-power DC) | 14–16 hours | Modest (200–250 kW) | Often feasible, as long as buses arrive early and have moderate route energy use. |
| Mid-size suburban depot | 30–50 buses | 15–25 × 60 kW DC | 10–12 hours | Medium (600–900 kW) | Feasible if demand limit is aligned with charger capacity; constrained if the limit is set too low. |
| Large urban depot | 60–100+ buses | 30–50 × 60–120 kW DC | 8–10 hours | High (1–2 MW or more) | Often demand-limited; may require staggered route blocks, higher power chargers, or utility upgrades. |
Use these patterns as a starting point when running your own scenarios: for example, current depot vs. expanded charger count, or conservative vs. aggressive demand limits.
This scheduler is designed for early-stage planning and concept evaluation. It intentionally simplifies several real-world factors:
Because of these assumptions, you should treat results as directional rather than definitive. For detailed engineering design, interconnection studies, or procurement decisions, always pair this tool with utility-side modeling, charger vendor input, and route-block level scheduling analysis.
If the results suggest your depot cannot fully charge the fleet within the available window or that demand charges become excessive, consider the following adjustments:
By iterating a few scenarios in the scheduler and then validating promising options with your utility and vendors, you can design a depot that reliably supports full fleet electrification.
School districts all over the world are electrifying their bus fleets to slash diesel exhaust near students, tap into federal incentives, and reduce long-term operating costs. Yet most depots were never designed to move megawatt-hours overnight. Routes end within a narrow window, departure times are fixed by bell schedules, and drivers expect predictable workflows. Generic EV calculators rarely capture the nuance of dozens of identical vehicles stacking up outside the garage right as peak demand pricing hits. This tool focuses on the constraints unique to school transportation: tight charging windows, cold weather reserves, managed demand limits, and the economic implications of on-peak drift.
The calculator blends electrical engineering fundamentals with fleet operations. Rather than assuming unlimited charger availability, it tests whether your actual port count can cycle every vehicle through the queue before sunrise. It also highlights how much demand headroom you need to avoid punitive tariffs and calculates the cost of straying into the demand charge zone. With those insights, transportation directors can defend capital plans, schedule driver shifts, and coordinate with utilities on managed charging agreements.
Each bus arrives at a certain state of charge (SoC) and must reach a target SoC before dispatch. The calculator converts those percentages into usable energy by multiplying battery capacity by the difference in SoC, expressed mathematically as t
Charging hours per bus are calculated by dividing energy required per vehicle by charger power. Total charging hours for the fleet scale with the number of buses and available ports. Because real operations include a safety margin, the calculator adds the operational reserve percentage to the energy requirement to ensure buses can handle detours or cold weather auxiliary loads. Average simultaneous load is computed by dividing total energy by the available window. The tool then checks that the implied power draw per hour, multiplied by charger power, stays below the number of available ports. If not, it highlights the shortfall and suggests extra charger sessions.
Demand charges can dominate depot bills, so the model compares peak load to the site’s contractual limit. When the product of charger power and simultaneous sessions exceeds the limit, the calculator estimates additional monthly costs using the demand charge rate. It further breaks out energy costs assuming all charging occurs off-peak up to the window limit; any remaining hours are billed at the on-peak tariff. That allows facilities to test whether extending the window—even by one hour—pays for itself through avoided peak energy.
Suppose a district operates 48 buses with 210 kWh packs. After afternoon drop-off, buses return at 35% SoC and must leave at 90%. Each bus uses 145 kWh on its route and the district keeps a 10% operational buffer for snow days. Energy per bus therefore equals the greater of the SoC delta (115 kWh) and the route energy plus buffer (159.5 kWh). The model uses 159.5 kWh because routes dominate. With 18 charging ports delivering 60 kW, each bus needs 2.66 hours on a charger. Cycling all vehicles through requires 7.09 total charger-days (48 buses × 2.66 hours ÷ 18 ports), which fits comfortably inside the 12-hour overnight window even after accounting for connector swaps.
Average simultaneous power draw is 636 kW (total energy of 7,656 kWh ÷ 12 hours). The tool compares that load to the 900 kW site demand limit and signals that the fleet remains within the cap. If the window shrank to 8 hours, however, average load would climb to 957 kW, triggering demand charges of roughly $684 per night. The calculator also estimates energy costs: 7,656 kWh at $0.08 totals $612. If 10% spills into the on-peak block, the excess 766 kWh costs $138 at $0.18, giving a nightly total of $750. Results also surface the slack time available; in this case, the depot has 4.9 hours of idle port capacity for maintenance or opportunistic vehicle-to-grid services.
Use the scenario table below to stress-test charger counts and windows during capital planning meetings. Values are illustrative and not tied to your form submission.
| Scenario | Chargers | Window (h) | Peak Load (kW) | Demand Charges |
|---|---|---|---|---|
| Minimal Compliance | 12 | 10 | 960 | $720/night |
| Recommended Baseline | 18 | 12 | 636 | $0/night |
| V2G-Ready Expansion | 24 | 12 | 720 | $0/night |
The patterns reveal that adding chargers can actually lower monthly bills when they allow slower, flatter charging profiles that avoid demand peaks. That insight is often counterintuitive to budget reviewers, so bring the table to your next board presentation.
The calculator assumes chargers operate at their nameplate power and that buses can plug in immediately upon arrival. In reality, drivers may stage vehicles or maintenance staff may need extra time to rotate connectors. To reflect those operational inefficiencies, widen the reserve percentage or lower the available window. Battery cold-weather derating is not explicitly modeled; consider increasing route energy in winter to reflect heating loads. Likewise, degradation over time means batteries will eventually require more plug-in hours. Revisit the model annually to confirm headroom.
For a deeper dive into electrical infrastructure sizing, pair this tool with the EV Fleet Charging Load Balance Planner or coordinate tariff analysis using the EV Charger Load Management Planner. Districts testing vehicle-to-grid revenue opportunities can reference the Vehicle-to-Grid Backup Coverage Calculator to layer in ancillary services income. Together, these resources build a holistic picture of capital needs, operational procedures, and rate impacts.
Transportation directors can translate the results into driver shift schedules, designating time slots for plugging in and swapping cables. Facility managers should compare the recommended peak load to existing service transformers; if the modeled demand exceeds infrastructure capacity, share the numbers with your utility early. Grant writers can use the avoided demand charges and emissions reductions to strengthen funding applications. Finally, share the schedule with principals and parents to demonstrate that electric buses will be ready every morning, rain or shine. Confidence in reliability is the key to building community support for continued electrification.